Glass Bottle Site, Pembroke Quarter Phase 1, Dublin
Job Type: Demolition
Value:
€950,000
Building Type:
Commercial
Programme Duration:
6 months, Commenced 3 May 2023
Scope;
- Establishment of site welfare facilities including pad foundations for offices, hoarding, fencing and walkways
- Formation of pilling matt
- Formation of site ramps to podium
- Excavation of crane bases
- Attendances to pilling rig
- Installation of sub ground drainage including all bedding and surrounds
- Installation of above ground drainage to under croft
- Diversions/connections to main line drainage
- Installation of petrol interceptor and combined insitu manholes
- Testing and commissioning of all installations
Site Location:
Glass Bottle Site, Pembroke Quarter Phase 1, Dublin
Start Date:
November 2023
End Date:
May 2023
Contacting Authority:
John Sisk & Sons
Role of Company:
Address of Contacting Authority:
Wilton Works, Naas Road, Dublin 22, Ireland